Detailed Report · as of 2026-08-17

Naman Xana

Mumbai's costliest square foot, on land the corporation still owns. · RERA P51900018769

Worli Sea Face · Khan Abdul Gaffar Khan Road · G/South · 400018 · leasehold (perpetual, municipal)

Overall Score5.5/10as of 2026-08-17

The sea view is real, permanent and worth paying for — the paperwork underneath it is none of those things.

Flags
  1. The separate municipal lease for this plot was still unexecuted at the only title opinion, dated 2018.
  2. No occupation certificate exists, and the permission on record covers 35 of the 41 sanctioned floors.

The five things that decide it
1Thirty-seven per cent of the sanctioned floor area is granted against seventy-six tenements that exist on the drawings as numbered rooms inside the duplexes, and the final approval for that device is still an open condition.
2Ten charges subsist over the land and the development rights, including 125 crore rupees of debentures and one mortgage securing a third party's borrowings, while the public record states there is no encumbrance at all.
3There is no occupation certificate, the permission on record covers 35 of 41 floors and lapsed in July 2025, and four approvals remain open — including the landlord corporation's own consent.
4The western sea aspect returns no obstruction and no future threat of any kind, and because the lowest home stands 56 metres above the road, that clearance belongs to every apartment rather than only the top ones.
5The floor area more than tripled after the plot's coastal floor-space freeze lifted in 2021, and the largest single block of it — 37 per cent — changed basis from a public car park to seventy-six tenements inside four plan amendments that are missing from the file.
FVL — Rexray's index · F Fundamentals · V Value · L Livability · each pillar is the average of its scored attributes, scored 0–10: Weak (<4) · Mixed (4–6) · Fair (6–7.5) · Strong (7.5+) · the verdict is set separately, by hard-stop rules · Scoring Methodology →

Fundamentals

4.8/10Mixed

Pillar score is the average of the scored attributes below; some attributes are qualitative and carry questions rather than a number.

Clear Title4.5/10
A perpetual municipal lease with four documentary gaps that have never been closed
  • The land is Municipal Corporation freehold let on a lease in PERPETUITY from 1937 — a genuinely strong tenure with no expiry and none of the renewal-premium exposure that burdens housing-board and collector leases.
  • Against that sit four documentary gaps that have never been closed: the separate lease for this sub-divided plot was still unexecuted when the only title opinion was written in November 2018; that opinion is now nearly eight years old and is expressly subject to the mortgages and the litigation; ten charges subsist including 125 crore rupees of debentures secured on the very development rights that constitute the project and one mortgage securing a third party's borrowings; and no registry search of any kind, of any date, exists in the file.
  • The perpetual term is the strength and it should not be lost in the caveats.
  • There is no expiry, no renewal event and none of the renewal-premium exposure that sits on housing-board and collector leases elsewhere in the Worli-Prabhadevi set.
  • What replaces it is a transfer premium: the corporation levies one when leasehold rights change hands, the promoters paid a little over four crore rupees of it in 2015, and the promoters' own writ petition — which has been pending since 2015 and already lost its constitutional limb in February 2015 — is a challenge to how that premium is calculated.
  • Whatever it costs, it is the mechanism that will price a future conveyance to the society.
Understand “Clear Title” on the X-Ray page ↗
Delivery5.0/10
Topped out and close to certification, with four approvals still outstanding
  • The structure is topped out and the project is close to occupation, which moves the live risk from building to certifying.
  • But no occupation certificate of any kind exists, the building permission on record covers 35 of the 41 sanctioned floors and lapsed in July 2025, and four separate approvals remain open conditions of the latest sanction — the corporation's own estate department No-Objection Certificate as landlord, the open-space-deficiency condonation premium, the contravening-structures final No-Objection Certificate, and a fresh high-rise committee clearance for anything above 149.47 metres.
  • Set against a plot that took eight years to reach its first sanction and stalled again mid-build, the offsetting evidence is real: eleven registered sales, the most recent in July 2026, and thirteen floors of certificate in fourteen months once the stall broke.

Still outstanding as conditions of the latest sanction:

  • The municipal estate department's clearance — the landlord's own consent, required before every further permission and before occupation.
  • The premium for condoning the plot's deficiency in open space.
  • The final clearance for the project-affected and contravening structures.
  • A revised high-rise committee approval before any permission above 149.47 metres, which falls between the 37th and 38th floors.
  • The plot's history is the context.
  • Permission was applied for in December 2008 and first granted in April 2016 — eight years with nothing built.
  • Plinth followed in 2017, and by May 2022 the certificate had reached only the top of the parking podium, with a 2020 filing recording that work had not restarted after the lockdown.
  • From 2023 the pace changes completely: thirteen floors of certificate in fourteen months.
  • Why the delay matters differently once the regulatory calendar is laid alongside it: this is a coastal-zone plot, and the rules in force for most of the project's life froze its floor-area entitlement at 1991 levels.
  • The scheme actually sanctioned and plinth-certified in 2017 was three wings of 2,919 square metres — which is what a 1991-frozen entitlement buys on a plot this size.
  • The rules that lifted the freeze became operative in Mumbai on 30 September 2021.
  • The first of the eight plan amendments that produced this tower is dated 29 April 2022, and the building permission moved from plinth to the top of the parking podium a week later.
  • The correlation is exact; causation is nowhere documented and is not claimed here.
Understand “Delivery” on the X-Ray page ↗
Developer Compliance4.0/10
Filings are current; the public record understates the building by nearly half
  • Quarterly filings are current — the architect's completion certificate runs to April 2026 and the inventory disclosure to September 2025 — and there are no complaints or appeals.
  • The public record itself is the problem.
  • The portal states a sanctioned built-up area of 7,551 square metres against the approved plan's 13,910, understating the building by nearly half.
  • The apartment schedule, the habitable-floor count and the unit summary are entirely blank on a project registered for close to eight years.
  • Three rows of the building-permission table render empty, and a permission dated January 2026 is listed with no document attached.
  • The encumbrance field reads 'No' while the promoters' own certificate, filed in the portal's own finance section, lists ten.

Eighteen years, two stalls, and a building that more than tripled in size — the sequence, from the documents:

  • December 2008 — development permission applied for. Nothing is built for eight years.
  • April 2016 — first municipal approval, requiring a coastal-zone clearance that is not in the file.
  • July 2017 — first building permission, for the plinth only, of a three-wing scheme of 2,919 square metres.
  • October 2018 — the developer files both computations with the regulator: 2,922 square metres under the old rules, 13,956 gross under the new.
  • July 2020 — a filing records that work has not restarted after the lockdown, with four labourers available against need and bookings below half.
  • 30 September 2021 — Mumbai's coastal zone management plan is approved and the floor-area freeze lifts.
  • April and May 2022 — the first plan amendment, and permission moves from plinth to the top of the 14th parking floor.
  • July 2023 — the 27th floor. May 2025 — the 35th. Thirteen floors of certificate in fourteen months once the stall breaks.
  • July 2025 — the governing sanction: 41 floors, 13,910 square metres gross.

And where the extra floor area came from — a 3.53-times increase on a plot that never changed size:

  • Base entitlement, 3,437 square metres — 33 per cent. The rate itself never moved from 1.33; the figure grew only because the current plan applies it to the gross plot rather than after a recreation-ground deduction.
  • Premium floor space bought from the corporation, 2,171 square metres — 21 per cent. Raised from 0.73 to 0.84 along the way, and payment is a condition of further permission.
  • Transferable development rights, 884 square metres — 9 per cent.
  • The incentive head, 3,814 square metres — 37 per cent, and the largest single block. In 2018 this was a public car park of 165 spaces to be handed to the corporation free of cost. In the 2025 sanction it is instead an entitlement computed on seventy-six tenements, and there is no public car park anywhere on the drawings.
  • Fungible compensatory area of 3,604 square metres sits on top of all of it, taking the gross to 13,910.
  • The swap in that fourth line happened inside the four plan-amendment letters that are missing from the file.
  • It is the single most consequential undocumented event in this dossier, and it is what the still-outstanding contravening-structures clearance attaches to.
Understand “Developer Compliance” on the X-Ray page ↗
Brochure-vs-Reality5.5/10
The developer claims almost nothing, and the one claim it makes is true
  • Unusually restrained official marketing, and the core claim is true.
  • The developer's own page quotes no floor count, no unit count, no price and no possession date — configuration and size are both 'on request' — and its one substantive claim, ocean views along Worli Sea Face, is confirmed by the sightline analysis.
  • The inflated numbers in circulation, 44 storeys and 22 residences against 41 sanctioned floors and 19 disclosed homes, together with a pool, spa, restaurants, sports courts and electric-vehicle charging that appear nowhere on the approved drawings, come from third-party listings rather than the promoter.
  • What pulls the score down is omission rather than overstatement: nothing anywhere discloses the leasehold tenure, the subsisting charges, the open approvals, or that thirty-seven per cent of the floor area rests on rooms counted as separate tenements.
  • Substantiated — ocean views along Worli Sea Face. Confirmed by the sightline analysis on three arcs.
  • Substantiated — column-free layouts. The living, dining and lounge band runs clear across the full plate width on the approved drawings.
  • Contradicted — 44 storeys and 22 residences. Forty-one floors are sanctioned and nineteen homes are disclosed. Both claims are third-party, not the promoter's.
  • Contradicted — pool, spa, restaurants, sports courts and electric-vehicle charging. The approved set draws a 279-square-metre gym, a society office and an unlabelled deck, and the project architect's own filing marks most of the rest as not proposed.
  • Omitted everywhere — the leasehold tenure, the ten charges, the four open approvals, and the seventy-six rooms counted as tenements.
Understand “Brochure-vs-Reality” on the X-Ray page ↗

Value

6.4/10Fair

Pillar score is the average of the scored attributes below; some attributes are qualitative and carry questions rather than a number.

View8.5/10
The best-protected sea aspect in the Worli set, and the lowest home is 56 metres up
  • The best-protected sea aspect in the Worli set, and the protection is structural rather than lucky.
  • The sightline analysis returns no obstruction and no pipeline threat at all on the west, north-west and south-west; the plot's seaward boundary is the 27.45-metre seafront road itself, with the promenade and the coastal regulation zone beyond, and the north is open across an 18-metre road because this is a corner plot.
  • On top of that, fifteen non-habitable levels sit under the first apartment, so the lowest home in the building stands 56 metres up — anything shorter than roughly eighteen conventional storeys is a non-event for every home here, not just the upper ones.
  • The deduction is that the other half of the compass is permanently compromised: two towers to the east and south-east are taller than this building's own roof, so those arcs never clear at any floor, and three pipeline schemes to the north-east would behave the same way if built.

Read by compass arc, at every floor:

  • West, north-west and south-west — open sea over the promenade. No obstruction and no proposed scheme of any kind. Protected by a 27.45-metre public road and the coastal regulation zone.
  • North — open across an 18-metre road. This is the corner-plot dividend: the north side is a street, not a party wall.
  • South — a distant cluster 1.2 kilometres away tops out around the 36th floor; the immediate southern neighbour is a smaller building and is not in the sightline of any home here.
  • North-east — city view today, with two partial blocks clearing around the 29th and 38th floors. Three proposed schemes, the nearest 400 metres away, would each be taller than this building's own roof and would therefore block their slice at every floor if built.
  • East — permanently compromised. A 239-metre tower a kilometre away is 78 metres taller than this building's terrace, so no floor clears it.
  • South-east — the weakest arc, a little over half blocked, and a 217-metre tower 700 metres away is again taller than this building.
  • The pattern is worth stating plainly: the sea side is permanent and the city side is permanently compromised.
  • Height buys nothing on the eastern half of the compass, because the buildings there are already taller than this one will ever be.
Naman Xana — the plot and what surrounds it
Rexray View Map: Naman Xana and its surrounding development
Understand “View” on the X-Ray page ↗
Layout & Living6.0/10
An excellent plate held back by a 6.3-square-metre maid's room
  • Roughly 70 per cent efficient, which is mid-pack for the Worli set — better than a second-row Worli plate at 66 per cent, below a well-organised tower at 74 to 81 per cent.
  • The plate itself is excellent: the living, dining and lounge band runs column-free across the full 24-metre width, the envelope is a clean rectangle with the circulation core pushed outboard so that three faces stay habitable, and there are four balconies including one deep 22.7-square-metre deck.
  • The entire deduction is the service provision — a single 6.3-square-metre maid's room with a 3.4-square-metre toilet in an 800-square-metre home transacting above 150 crore rupees.
  • At this efficiency the registered rate of about 2.5 lakh rupees a square foot on carpet is roughly 3.6 lakh on built-up.
What to ask the builder
  • The west-face glass specification — brand, glazing thickness, and the heat-trapping (SHGC / U-value) number.
Understand “Layout & Living” on the X-Ray page ↗
Non-RERA Area7.0/10
The lift lobby is a gift, not a charge; only a small service wing is in question
  • Narrow and mostly favourable.
  • With one apartment to a floor the 20-square-metre lift lobby outside the front door is drawn hatched and deducted in the plan's own area calculation — the buyer gets the use of it without paying for it, which is the lobby-as-bonus pattern and is not a finding.
  • The four balconies, about 62 square metres in all, are disclosed open decks and are not a finding either.
  • The only restricted-common-area candidate is a roughly 20-square-metre enclosed service wing — maid's room, servant toilet and two service passages — reached through a fire door from the pressurised lobby rather than through the flat's own entrance, yet counted inside the charged built-up line.
  • At about 3 per cent of carpet that is small.
  • How it is described and charged can only be confirmed from the registered agreement, which is not in the file.
Understand “Non-RERA Area” on the X-Ray page ↗
Pricing4.0/10
Mumbai's most expensive square foot, at twice the next-best building on its own street
  • Measured against the right comparable set — the seafront road itself, not the suburb — this is the most expensive residential square foot in Mumbai on registered data, and the premium is not marginal.
  • Three separately sourced registrations between May 2025 and July 2026 sit at 2.45 to 2.53 lakh rupees a square foot on carpet, against a government reckoner rate of 60,672 for this exact zone and against 1.25 lakh registered on the same road in August 2025 for a comparable new-build.
  • That is roughly four times the reckoner and roughly twice the next-best building on its own street.
  • Some of the gap is defensible and is scored elsewhere as an asset: a durable front-row aspect, a corner plot, one home per floor, a column-free plate.
  • But a two-times premium over the same frontage leaves very little margin for error, and at the top of any market the downside protection is thinnest.
  • Two adjustments belong on top of the headline rate rather than inside it — fit-out, if the homes are delivered bare shell, and the 70 per cent efficiency that turns 2.5 lakh on carpet into about 3.6 lakh on built-up.
  • May 2025 — 225.76 crore rupees for 9,214 square feet of carpet, about 2.45 lakh a square foot.
  • May 2026 — 294 crore rupees for two apartments totalling 11,620 square feet, about 2.53 lakh a square foot.
  • July 2026 — 162.2 crore rupees for 6,458 square feet, about 2.50 lakh a square foot. That is exactly the size of a single-floor home here.
  • A widely reported 639-crore-rupee sale at 2.83 lakh a square foot is carried at lower confidence: no registration platform is named in any account of it.
  • The comparison that matters is the frontage, not the suburb.
  • On the same seafront road a comparable new building registered at about 1.25 lakh a square foot in August 2025; one row inland, a well-known trophy tower registered at about 1.51 lakh in July 2026; the government reckoner rate for this exact zone is 60,672.
What to ask the builder
  • What is the all-in cost — including stamp duty, registration and goods-and-services tax (GST)?
  • What is the rate on the area I actually own (carpet plus deck) versus the marketed area?
  • What have recent apartments in this building / micro-market actually registered at?
Understand “Pricing” on the X-Ray page ↗

Livability

6.8/10Fair

Pillar score is the average of the scored attributes below; some attributes are qualitative and carry questions rather than a number.

Compound Density7.5/10
Nineteen homes on six-tenths of an acre, with no rehabilitation building on the plot
  • Nineteen homes on a plot of about six-tenths of an acre, one apartment to a floor across most of the stack, with duplex pairings at six levels.
  • No rehabilitation building, no slum-scheme tower and no second sale tower shares the compound — this is a single building on its own ground, and intra-plot density is among the lowest in the Worli set.
  • Two offsets keep it off the top of the band: the plot is deficient in open space and the deficiency is bought off with a premium payable before further permission, and the approved plan accounts for 76 rooms inside these apartments as separate tenements, which is why the building's own parking statement is computed on eighty-nine.
Understand “Compound Density” on the X-Ray page ↗
Neighbourhood6.0/10
The west is settled; the eastern half of the compass is about to get taller
  • The immediate surroundings are as good as this corridor offers: a seafront road and promenade to the west, an 18-metre road to the north, a smaller co-operative building to the south and an institutional research building to the east.
  • The medium-horizon picture is busier.
  • A slum-rehabilitation cluster sits about 510 metres to the south-east and a police-quarters redevelopment about 640 metres to the north-east, both of which would rise well above this building's own roof.
  • The same seafront frontage is actively redeveloping, with at least three registered schemes on or near it targeting completion between 2028 and 2029, including one on another corporation-estate plot.
  • None of that touches the western aspect; all of it will be visible from the eastern half of the compass and will be felt on the roads.
Understand “Neighbourhood” on the X-Ray page ↗
Peak-Hour Connectivity9.5/10
One minute to the coastal road — the strongest access figure in the Worli set
  • One minute from the gate to the nearest coastal-road entry, confirmed on the ground.
  • The plot fronts the seafront road itself, so the coastal road is effectively at the door.
  • This is the strongest access figure in the Worli set and it is a durable one — it depends on a road that already exists rather than on a proposed link.
Fixable? Builders like to sell connectivity as kilometres from a landmark — but the real test is time, not distance: how long you would actually be stuck, at peak hour, just getting to a fast arterial like a Sea Link or Coastal Road on-ramp. The access route and the on-ramp are municipal and outside the developer's control, so there is no fix to offer — only an honest read of the peak-hour reality today and the area's trajectory by 2032, once the surrounding pipeline has built out.
Understand “Peak-Hour Connectivity” on the X-Ray page ↗
Kitchen Ventilation9.0/10
The kitchen has two external walls and a weathershed; the air path is unambiguous
  • Pass.
  • The kitchen sits at an outer corner of the plate with two external walls, both drawn as glazed window bands and the outer one shaded by a 1.2-metre weathershed.
  • It is not an internal kitchen and does not depend on a light-and-ventilation shaft or on mechanical extraction.
  • The air path is unambiguous on the approved plan.
Understand “Kitchen Ventilation” on the X-Ray page ↗
Lift Wait6.0/10
Three lifts, nineteen households, and a travel height of 145 metres
  • Grade B to C across the luxury band — a waiting interval of roughly 41 seconds at the fast end of plausible lift speeds and 54 seconds at the slow end, on three passenger lifts serving 24 residential levels with a travel height near 145 metres, plus a fire lift and a dedicated firemen's evacuation lift.
  • No lift schedule is printed anywhere on the approved drawings, so speed and capacity were swept as a band and the conservative grade sealed.
  • Two things pull in opposite directions.
  • In the building's favour, there are only nineteen households, so the real morning queue is trivial.
  • Against it, the same three lifts serve every level from the third basement to the fortieth floor, including thirteen parking floors — and because most bays are reachable only by car lift, residents ride the passenger lifts to their parking level, a load the standard model does not capture.
Understand “Lift Wait” on the X-Ray page ↗
Water Adequacy5.0/10
The approvals state no water-connection count, so this cannot be closed from the file
  • Neutral, and honestly so.
  • The base municipal approval carries a single water-and-sewerage charge condition, a requirement for the hydraulic engineer's remarks, a sewer-line clearance and rainwater harvesting — but it states no water-connection count anywhere, so the usual comparison between sanctioned connections and unit count cannot be made from this file.
  • The question is sharper here than usual because the approved plan describes eighty-nine tenements while the sale disclosure describes nineteen homes: the two configurations imply very different demand.
  • The hydraulic engineer's clearance and its stated capacity are the document to ask for.
Understand “Water Adequacy” on the X-Ray page ↗
Parking3.5/10
You can drive to seventeen of sixty-three bays; for the rest you wait for a lift
  • A two-tier building, and the worse tier is much the larger.
  • A helical double-spiral ramp on the west of the plot climbs from the third basement to the first parking levels and stops; from the fourth floor upward, access is by car lift only.
  • That leaves 17 of 63 bays drivable and 46 reachable only by one of four car lifts, with bays as high as the fourteenth floor, 45 metres above the road.
  • The bays themselves are ordinary self-park spaces — there is no stacker, puzzle or mechanical system anywhere — and retrieval arithmetic is not the problem: four lifts against nineteen households returns a peak wait of under two and a half minutes.
  • What holds the score at the bottom of the two-tier band is the height of the stack, no visitor parking at all on either the plan or the public record, and no electric-vehicle provision drawn anywhere despite listings advertising it.
  • The ratio is generous, at more than three bays a home.
  • Bay allotment is still open — eleven of sixty-three are allotted, tracking the eleven sales — so the level is negotiable, and it is worth negotiating.
Understand “Parking” on the X-Ray page ↗
Build Planning & Qualitynot yet scored
A checklist to verify with the builder — Rexray will score this attribute as the field database grows.

Rexray's database will, over time, be enriched with the attention to detail and quality ethos of each builder. For now, below is the checklist you should verify with the builder before you decide.

What to ask the builder
  • Who's the architect, and what comparable have they delivered?
  • Do the lobbies need lights during the day?
  • Gym/pool/lobby sized for how many residents? (gym sqft / residents)
  • Does this unit's layout meet your Vastu requirements (entry, kitchen, master)?
  • Can a fire tender or an ambulance reach the lobby?
  • Who is actually building it?
  • Mivan or conventional — and how are the tie-holes grouted and cracks controlled?
  • What's the realistic floor-cycle, and how does the monsoon factor in?
  • Which steel/cement? Facade glazing spec? MEP contractor? STP/solar?
  • Which marble/fittings exactly? Which window system? VRV brand?
  • Deck/bathroom waterproofing system? How's the facade sealed into the structure?
  • Gypsum or block internal walls — and are the party walls insulated?
  • Does the back-up generator power my whole flat, or only the common areas?
  • Is the parking solo, tandem, or a mechanical stack — and how wide are the bays?
Understand “Build Planning & Quality” on the X-Ray page ↗
Community8.0/10
Nineteen homes, eleven sold, an ultra-high-net-worth profile with no churn
  • Nineteen homes of 600 to 1,048 square metres carpet, sold at rates that make this the most expensive building per square foot in the city, to buyers who on the public record include a leading industrial family's investment vehicle and an overseas healthcare-software founder's family.
  • Eleven of nineteen are sold, all of them on the floors the plan draws as single apartments.
  • That is an ultra-high-net-worth, professionally advised, low-turnover profile with essentially no rental or investor churn, and no rehabilitation or project-affected component shares the building.
  • The one open question is what happens to the eight unsold homes, all of which sit on the floors the plan draws as numbered rooms.
What to ask the builder
  • What is the ticket-size range in the building — the gap between the cheapest and the most expensive home?
  • Is the building vegetarian-only, or skewed to a single community?
  • Is it owner-occupied, or investor- and tenant-heavy?
  • What is the pet policy?
Understand “Community” on the X-Ray page ↗

Findings register

15 findings · severity-ranked

Every marketed claim set against the documented fact, sourced. Critical and high first.

HIGH
Thirty-seven per cent of the building's floor area is bought by counting the rooms of its duplexes as separate tenements
MarketedElegantly crafted luxury residences with expansive layouts
DocumentedProforma A item 12 grants 3,814.44 sqm — 37.0% of the entire permissible built-up area of 10,306.40 sqm — 'As Per DCR 33(12)(B) [2542.96 sq.mt / 33.46 sq.mt 76 nos] x 1.5'. The drawings realise those 76 tenements as 76 ROOMS, each labelled 'M.P. ROOM / CONTR. STRCT.' with its own carpet area and usually its own toilet, sitting inside the apartments on floors 16 to 20 and 36 to 38. Sheet 21 is headed 'TABLE 21 - FOR PAP FLATS' and lists the same 76, every one named 'Contravening Structure' with a blank occupant column. The car parking statement on sheet 1 sizes the building's statutory parking on eighty-nine tenements. Both 2025 sanction letters still require a 'PAP / Contravening structures final No-Objection Certificate' that is not in the Worli set.
The largest single block of this building's floor area was granted against seventy-six tenements that exist on the drawings as individually-numbered rooms inside luxury duplexes.
Source: government filings, registered documents, Rexray analysis
HIGH
Further construction permission is gated on four outstanding approvals, one of them the landlord's
MarketedPossession August 2027
DocumentedThe latest sanction requires, before the commencement certificate can be endorsed: the No-Objection Certificate of the MCGM Estate Department; payment of a premium towards condonation of OPEN SPACE DEFICIENCY; the final No-Objection Certificate for PAP / contravening structures; and, before any Commencement Certificate above a building height of 149.47 metres, a REVISED High Rise Committee No-Objection Certificate. None of the four is in the document set.
Four separate approvals stand between this building and its remaining floors, and one of them is the landlord's own consent.
Source: government filings
HIGH
Ten charges subsist, including 125 crore of debentures on the floor area (FSI) rights and a mortgage securing a third party
MarketedThe MahaRERA portal states 'Do you have Financial Encumberance: No'
DocumentedThe promoters' own certificate, filed in the portal's finance-disclosure section on 19/07/2025, lists ten subsisting items: seven Indiabulls instruments over the leasehold rights, the floor area (FSI) rights and the receivables; and a Deed of Confirmation read with a Debenture Trust Deed of 16/02/2016 by which Naman mortgaged its floor area (FSI) rights to IDBI Trusteeship Services as security for Rs.125 CRORE of debentures. One of the Indiabulls supplemental mortgages, BBE3/6879/2017, secures loan facilities availed by a third party, Sujay Infraprojects Private Limited.
The portal says there is no financial encumbrance; the promoters' own document filed on the portal lists ten.
Source: registered documents
MED-HIGH
The lease for this plot has never been executed
MarketedNot addressed in any marketing seen
DocumentedThe land is owned by MCGM and held under an Indenture of Lease dated 31/03/1952 for a term IN PERPETUITY from 18/01/1937 — but that lease demises the LARGER 3,938.83 sqm parcel. MCGM gave no-objection to sub-division into Plot 95 and Plot 95-A in 1980 and 1981, and a 1981 MCGM letter set out the cost of preparing NEW leases for the two sub-divided plots. As at the only title opinion in the Worli set, 'the separate lease in respect of the said Property by the MCGM in favour of Karp... after sanction of sub-division... is pending to be executed.'
The lessee holds no lease instrument for the plot this tower stands on; its rights rest on a 1952 lease of a larger parcel plus forty-year-old sub-division letters.
Source: registered documents
MEDIUM
Three completion dates are on the record and the structure is ahead of the last certified filing
MarketedPossession August 2027 (some listings October 2027)
DocumentedForm B declares 'the time period within which the proposed project shall be completed by Promoters, shall be on or before, 31st August 2026'. The portal shows 28/08/2027. Marketing shows August or October 2027. As certified by the project architect on 09/04/2026: superstructure slabs 80%, internal walls and plaster 40%, SANITARY FITTINGS 0%, lifts, fire-fighting and finishing 30%, external plumbing and elevation 40%.
Three different completion dates are on the record, and the earliest of them falls two weeks after this file was compiled.
Source: registered documents, government filings, REXRAY-FIELD
MEDIUM
Three quarters of the parking is reachable only by car lift, up to the fourteenth floor
Marketed'11 Floors of Parking'
DocumentedA helical double-spiral ramp on the west of the plot climbs from the 3rd basement to the 1st-floor podium AND STOPS. Sheets 8, 9 and 10 carry no ramp and no up/down arrows. The 3rd, 4th and 5th to 14th floors — holding 46 of the building's 63 car bays and all 25 two-wheeler slots — are served only by four car lifts, whose machine rooms sit on the 15th service floor. The portal records zero visitor parking, and no EV charging provision is drawn anywhere on the 21-sheet set.
You can drive to seventeen of the sixty-three bays; for the other forty-six you wait for a car lift.
Source: government filings, registered documents, REXRAY-FIELD
MEDIUM
The public parking lot that justified the 2018 floor area (FSI) has disappeared from the 2025 sanction
MarketedNot addressed in any marketing seen
DocumentedThe 2018 declaration to MahaRERA records that the development was approved with a multi-storeyed Public Parking Lot under DCR 33(24), with an LOI issued on 31/08/2018 for 165 LMV public parking spaces across three basements, ground and the 1st to 4th podium levels, generating additional floor area (FSI) of 4,125 sqm, with a separate entry and exit, 'which will be handed over to the MCGM after construction, free of cost'. The governing 2025 sanctioned set contains no public parking lot at all: nothing is labelled or hatched as public parking, there is one entry gate and one exit gate serving the whole plot, and all 63 bays are counted against the residential requirement. The incentive-floor area (FSI) head in the 2025 Proforma is 33(12)(B) at 3,814.44 sqm.
One hundred and sixty-five public parking spaces and the regulation that generated them are in the 2018 filing and absent from the 2025 sanction, and nothing in the file explains the change.
Source: registered documents, government filings, Rexray analysis
MEDIUM
The portal understates the sanctioned building by nearly half and leaves its unit tables blank
MarketedMahaRERA registered, 'no litigations' per aggregator pages
DocumentedThe portal shows Sanctioned Built-up Area of 7,551.03 sqm against the governing plan's proposed 13,910.04 sqm. The Summary of Apartments table, the habitable-floor count and the sanctioned-apartment count are entirely blank on a project registered for 7.7 years with 11 units sold. The Commencement Certificate table renders rows 1 to 3 blank with only rows 4 and 5 populated, and the 06/01/2026 Commencement Certificate it lists has no document attached. The financial-encumbrance field reads 'No'.
The public record of this project is materially thinner and materially wrong compared with its own approved drawings.
Source: registered documents, government filings
MEDIUM
Eighteen years from application to today, with two stalls and a floor area that more than tripled
MarketedNot addressed in any marketing seen
DocumentedDevelopment permission was applied for on 06/12/2008 and the first sanction issued on 18/04/2016 — eight years with nothing built. Plinth Commencement Certificate came in July 2017; by May 2022 the certificate had reached only the top of the 14th parking floor, and a July 2020 declaration records that work had not restarted after the lockdown with four labourers available against need. Over the same period the scheme changed from three low wings of 2,918.79 sqm to one 41-floor tower of 13,910.04 sqm gross.
The building that is being sold is more than three times the floor area of the scheme that was first approved on this plot, and it took two stalls and eight plan amendments to get there.
Source: government filings, registered documents, REXRAY-FIELD
MEDIUM
The plot's own approval required a coastal-zone clearance, and no such clearance is in the file
MarketedNot addressed anywhere in the developer's or brokers' material
DocumentedThe base municipal approval of April 2016 requires a clearance from the coastal zone management authority from the coastal regulation zone point of view. No such clearance, of any date, exists in the document set, and none could be found in open sources. Separately, the coastal rules in force when this project began froze the floor-area entitlement of landward plots at 1991 levels; the scheme actually sanctioned and plinth-certified in 2017 was a three-wing building of 2,918.79 square metres, consistent with that freeze. The rules that lifted the freeze became operative in Mumbai when the city's coastal zone management plan was approved on 30 September 2021. The first of the eight plan amendments that produced this 41-floor tower is dated 29 April 2022, and the building permission moved from plinth to the top of the 14th parking floor a week later.
This is a coastal-zone plot whose floor area was frozen at 1991 levels for most of its life; the tower's growth begins seven months after the freeze lifted, and the coastal clearance its own approval demanded is not in the file.
Source: government filings, registered documents, secondary sources, Rexray analysis
LOW-MED
The inflated claims are the brokers'; the developer's own page says almost nothing
MarketedDeveloper's own page: 'Situated along Mumbai's iconic Worli Sea-face... elegantly crafted luxury residences... serene ocean views'. Broker listings: '44-storey tower', '22 exclusive residences', pool, spa, restaurants, sports courts, EV charging.
DocumentedForty-one floors are sanctioned and the Commencement Certificate on record reaches the 35th. Nineteen units appear in the promoters' own disclosure. The sanctioned set draws a 278.92 sqm fitness centre, a 19.70 sqm society office and an unlabelled podium deck — and nothing else. The architect's own Form 1 marks 'Landscape garden, Yoga Zone, Jogging Track, Multipurpose Court, Net Cricket area, Skating Rink, Open air Gym' as PROPOSED = N. No EV provision is drawn on any sheet.
The amenity deck being sold is not on the approved drawings and the project's own architect has certified that most of it is not proposed.
Source: marketing, government filings, registered documents
LOW-MED
The building is deficient in open space and pays a premium to have it condoned
MarketedNot addressed in any marketing seen
DocumentedBoth 2025 sanction letters require 'Premium towards condonation of open space deficiency' to be paid before the commencement certificate can be endorsed. The recreation-ground provision is 681.57 sqm proposed against 516.88 sqm required, achieved across three separate diagrams on a plot where the helical ramp occupies most of the west margin.
The plot is tight enough that the open space had to be bought off with a premium.
Source: government filings
LOW-MED
Every approval is issued to a company that is not the RERA promoter
MarketedMarketed as a Naman Group project
DocumentedThe MahaRERA promoter is Shree Naman Residency Pvt. Ltd. Every approval in the Worli set — the building approval, all amended plan approvals and every commencement certificate — is issued to M/s. Karp Estate Pvt. Ltd., which the portal records as Promoter-Landowner on an Area Share basis. The sanctioned drawings' owner block reads 'M/s. KARP ESTATE PRIVATE LIMITED'. Every commencement certificate carries the standard warning: 'This permission does not entitle you to develop land which does not vest in you.'
The company that holds the approvals and the company registered as promoter are not the same company, and the agreement between them is not in the file.
Source: registered documents, government filings
LOW-MED
Sanction on this plot has been amended eight times in nine years and half the letters are missing
MarketedNot addressed in any marketing seen
DocumentedEight amended plan approvals are recited: 29.04.2022, 27.06.2023, 19.12.2024, 04.04.2025, 16.05.2025, file 337/7/Amend, and 22.07.2025. Only three letters are in the Worli set. The commencement certificate's own endorsement history steps from plinth in July 2017, to the top of the 14th parking floor in May 2022, to the 27th floor in July 2023, to the 35th in May 2025. The first commencement certificate was granted against an application dated 06/12/2008.
The design of this building has been re-sanctioned eight times, and four of the eight approval letters are not in the file.
Source: government filings
POSITIVE
The lowest home sits fifty-six metres up, and that is why the sea view holds
Marketed'Lifetime Arabian Sea views'
DocumentedFifteen non-habitable levels — three basements, a stilt, thirteen parking floors, three service levels and an amenity floor — sit below the first apartment, which is on the 16th floor at 56.15 metres above the road. The raycast returns ZERO walls and ZERO pipeline threats on the west, north-west and south-west arcs. The plot's west boundary is the 27.45 metre Khan Abdul Gaffar Khan Road, with the Worli Sea Face promenade and the CRZ shoreline beyond; the north boundary is the 18 metre Dr R G Thadani Marg.
This is a front-row corner plot whose sea arc is protected by a public road, a promenade and the coastal regulation zone — and whose lowest apartment already clears anything a neighbour could plausibly build.
Source: government filings, Rexray analysis, REXRAY-FIELD
Five questions to ask before you commit
  1. The approved plan labels the rooms of my apartment as seventy-six separate 'contravening structures' and grants thirty-seven per cent of the building's floor area on that basis. Show me the clearance that closes it, and tell me what my home is on the plan the occupation certificate will be issued against.
  2. The corporation owns this land and the separate lease for this plot was unexecuted in 2018. Show me the executed lease, a title opinion written after the eleven sales, and a current registry search — the one in the file is a self-certification from March 2023.
  3. Your own filing declares completion by 31 August 2026 and your architect certified sanitary fittings at zero per cent in April 2026. What is the real handover date, what compensation applies if it slips, and where is the permission dated 6 January 2026 that the record lists without a document?
  4. Which of the sixty-three car bays am I getting and on which level? Forty-six of them are reachable only by car lift. Commit the level in writing, and tell me the lift vendor, the maintenance contract and the uptime record.
  5. This is municipal estate land and the corporation has demanded premium on transfer of leasehold rights, which is what your own writ petition is about. What premium becomes payable when the building is conveyed to the society, and who bears it?
  6. Your 2016 approval required a coastal zone management authority clearance and there is none in the file. Show me the coastal clearance and the environmental clearance, and explain how the permissible floor area went from 2,919 square metres to 13,910 on the same plot.
Rexray — Real Estate X-Ray. This is a research view built from registered documents, government filings, and Rexray field analysis; it is not legal, financial, or investment advice. Verify every figure against the source documents before you transact.
© 2026 Rexray.AI