Thirty-year-old slum scheme, third developer, still at plinth. · RERA P51900079580 (Free Sale Wing)

The drawings are good. The paperwork is not.

Pillar scores are provisional roll-ups derived from the 16 attribute scores · FVL numeric scoring pending across all properties
nothing about the design or the entitlement is the problem: the index envelope is fully sanctioned and fully consumed, the floor numbering is honest, the unit plan matches the sale register floor by floor, the kitchens ventilate and the parking is self-park at 3.1 covered bays a home. The problems are time, money and paperwork: a scheme approved in 1996 that has lost two developers, a site at plinth with 11.7 per cent of a Rs.211 crore budget spent and no lender, and the only commencement certificate on file granted against a plan the authority cancelled four months later and valid for one year from October 2024.