MahaRERA P51900022056 (Ph-2, lapsed) + P51900002789 (Ph-1) · Provenance Land Pvt Ltd (GIC + RK Jatia) · CS 1H/136, Dr E Moses Rd, Worli · 228m, 41 residences
INVESTIGATEas of 06/26
Delivered branded ultra-luxury (full occupancy certificate (OC), clean title) with real operational drags — lifts, shared hotel/commercial access, and coastal-road time.
A delivered, clean-title, full-occupancy certificate (OC) branded ultra-luxury Worli home whose real story is not the marketed sea view but the operational reality — two of three lifts running, a chaotic shared hotel-and-commercial access, and a 16-minute coastal road.
Fundamentals are strong (F 6.75): full occupancy certificate (OC), a clear & marketable title, a fully-declared price and an institutional sponsor. The drags are experiential and current — only 2 of 3 lifts run (Grade D), a chaotic shared hotel/commercial access spine, a 16-minute coastal-road reality against a 'five-minute' claim, a charged-not-owned lobby, and a 'sea view' that is really the protected racecourse. INVESTIGATE those operational realities; a buyer who accepts them can reasonably SHORTLIST.
The five things that decide it
1Delivered & clean — full occupancy certificate (OC) received and a clear & marketable title (Kanga & Co.); the fundamentals are genuinely de-risked.
2Only two of three passenger lifts run today, so lift waits in this 228m tower model out at Grade D.
3One narrow private road serves the Four Seasons hotel (valet/event chaos), a rising ~60-floor commercial tower (the largest estate parcel) and the residences.
4Coastal-road access is ~16 minutes (not the marketed 'five'), and the 'sea view' is really the protected racecourse.
5About 17% of the area you pay for is an exclusive lobby you do not own (confirmed at agreement p.311).
Livability
5.6/10MixedPillar score is the average of the scored attributes below; some attributes are qualitative and carry questions rather than a number.
Compound Density6/10
Low on its own plot, dense at the estate
The residential plot itself is low-density: a single slender tower, 41 one-per-floor residences, no slum-rehab wing.
But the residences are the smallest-tower partner on a commercial-led estate — the ~60-floor commercial tower (the largest of the three parcels) sits between the hotel and the residences and dominates the setting.
Where this sits across the corpus · Compound Density
Rustomjee Crown9
Kalpataru One7
Sugee SeaKrest6
Birla Niyaara (Tower Silas)6
Four Seasons Private Residences6
Sugee Marina Bay5
Prestige Nautilus4
Embassy Citadel4
The Imperial Worli4
Aakasa4
Runwal Raaya3
Lodha Sea Face3
25 Downtown (Hubtown)2
Godrej Trilogy1
Four Seasons ranks 5 of 14.
Understand “Compound Density” on the X-Ray page ↗Neighbourhood4/10
Shared estate with hotel + commercial — gets chaotic
[Field] The Four Seasons hotel already generates weekend/event traffic — valets, functions — that makes the shared access chaotic, and the under-construction commercial tower will add to it.
The permanently-open racecourse to the east is the main offset. Net, the at-possession setting is an active hotel-plus-commercial estate, not a quiet residential compound.
Where this sits across the corpus · Neighbourhood
25 Downtown (Hubtown)7
Sugee Marina Bay6
Prestige Nautilus5
Sugee SeaKrest5
Lodha Sea Face5
The Imperial Worli5
Godrej Trilogy4
Rustomjee Crown4
Four Seasons Private Residences4
Aakasa4
Birla Niyaara (Tower Silas)3
Embassy Citadel3
Runwal Raaya2
Kalpataru One1
Four Seasons ranks 9 of 14.
Understand “Neighbourhood” on the X-Ray page ↗Peak-Hour Connectivity4/10
16 minutes to the coastal road — not five
- [Field] About 16 minutes to the Naman Xana Coastal Road access point on a weekday — against a marketed 'five minutes to the Bandra-Worli Sea Link'.
- Inland-eastern Worli plus the shared private spine cost real coastal-access time.
Fixable? Builders like to sell connectivity as kilometres from a landmark — but the real test is time, not distance: how long you would actually be stuck, at peak hour, just getting to a fast arterial like a Sea Link or Coastal Road on-ramp. The access route and the on-ramp are municipal and outside the developer's control, so there is no fix to offer — only an honest read of the peak-hour reality today and the area's trajectory by 2032, once the surrounding pipeline has built out.
Where this sits across the corpus · Peak-Hour Connectivity
Sugee Marina Bay9
Lodha Sea Face9
The Imperial Worli9
Godrej Trilogy8
Aakasa8
Prestige Nautilus7
Sugee SeaKrest7
25 Downtown (Hubtown)7
Rustomjee Crown5
Embassy Citadel5
Runwal Raaya5
Four Seasons Private Residences4
Kalpataru One2
Birla Niyaara (Tower Silas)2
Four Seasons ranks 12 of 14.
Understand “Peak-Hour Connectivity” on the X-Ray page ↗Kitchen Ventilation9/10
Pass — kitchen has an openable window
[Field] The kitchen has its own openable external window, so kitchen ventilation is fine. (The fixed glazing is the West living-room face, handled separately.)
Where this sits across the corpus · Kitchen Ventilation
Prestige Nautilus9
Sugee SeaKrest9
Kalpataru One9
Sugee Marina Bay9
Birla Niyaara (Tower Silas)9
25 Downtown (Hubtown)9
Rustomjee Crown9
Runwal Raaya9
Lodha Sea Face9
The Imperial Worli9
Four Seasons Private Residences9
Embassy Citadel8
Godrej Trilogy6
Aakasa6
Four Seasons ranks 11 of 14.
Understand “Kitchen Ventilation” on the X-Ray page ↗Lift Wait3/10
Only two of three lifts run — Grade D today
- Crowding is never the issue here (one home per floor).
- The problem is that only 2 of the 3 passenger lifts are operational, and over a 228m stack that models out at Grade D (roughly 62-75 second waits).
With the third lift running, the same core would be Grade B-to-C (~41-50s). Confirm the third car is commissioned and the rated lift speed.
Where this sits across the corpus · peak rush-hour lift wait
Runwal Raaya~5s
Birla Niyaara (Tower Silas)~19s
Sugee Marina Bay~20s
Sugee SeaKrest~21s
Rustomjee Crown~25s
Embassy Citadel~25s
Lodha Sea Face~25s
Godrej Trilogy~26s
Kalpataru One~28s
25 Downtown~29s
The Imperial Worli~38s
Aakasa~43s
Prestige Nautilus~47s
Four Seasons Private Residences~68s
Shorter is better. Four Seasons ranks 14 of 14.
What to ask the builder- Is the third passenger lift commissioned, and what is its rated speed?
Understand “Lift Wait” on the X-Ray page ↗Water Adequacy6/10
Residence has its own water sanction
- [Rexray field] check municipal building approval for tri-use water breakup.
- The residential municipal building approval (EB/1518/GS/A, CS 1H/136) is RESIDENCE-SPECIFIC, with standard water & sewerage conditions to AEWW 'G/South' (cond.19/24) and H.E.-No-Objection Certificate (cond.35).
- The hotel (Sub-Plot A1) and commercial (Sub-Plot A2) sit on separate sub-plots with separate approvals — the residential building has its own water sanction, not a shared/contested allocation.
- No adverse delta found; specific H.E.-No-Objection Certificate fixture count not separately extracted.
Where this sits across the corpus · Water Adequacy
Sugee SeaKrest8
Sugee Marina Bay8
Birla Niyaara (Tower Silas)7
Godrej Trilogy6
Kalpataru One6
Lodha Sea Face6
The Imperial Worli6
Four Seasons Private Residences6
Aakasa6
25 Downtown (Hubtown)5
Prestige Nautilus4
Rustomjee Crown4
Runwal Raaya4
Four Seasons ranks 8 of 13.
Understand “Water Adequacy” on the X-Ray page ↗Build Planning & Qualitynot yet scored
A checklist to verify with the builder — Rexray will score this attribute as the field database grows.
Rexray's database will, over time, be enriched with the attention to detail and quality ethos of each builder. For now, below is the checklist you should verify with the builder before you decide.
What to ask the builder- Who's the architect, and what comparable have they delivered?
- Do the lobbies need lights during the day?
- Gym/pool/lobby sized for how many residents? (gym sqft / residents)
- Does this unit's layout meet your Vastu requirements (entry, kitchen, master)?
- Can a fire tender or an ambulance reach the lobby?
- Who is actually building it?
- Mivan or conventional — and how are the tie-holes grouted and cracks controlled?
- What's the realistic floor-cycle, and how does the monsoon factor in?
- Which steel/cement? Facade glazing spec? MEP contractor? STP/solar?
- Which marble/fittings exactly? Which window system? VRV brand?
- Deck/bathroom waterproofing system? How's the facade sealed into the structure?
- Gypsum or block internal walls — and are the party walls insulated?
- Does the back-up generator power my whole flat, or only the common areas?
- Is the parking solo, tandem, or a mechanical stack — and how wide are the bays?
Understand “Build Planning & Quality” on the X-Ray page ↗Community7/10
HNI, branded-serviced community
- [Field] An HNI community: 41 limited-edition, Four-Seasons-serviced residences, single per floor, Rs.50 Cr+ entry, GIC-backed.
- Homogeneous UHNW/HNI, with a likely mix of owner-occupiers and serviced/investor-let owners under the Four Seasons asset-management programme.
What to ask the builder- What is the ticket-size range in the building — the gap between the cheapest and the most expensive home?
- Is the building vegetarian-only, or skewed to a single community?
- Is it owner-occupied, or investor- and tenant-heavy?
- What is the pet policy?
Understand “Community” on the X-Ray page ↗
Findings register
14 findings · severity-ranked
Every marketed claim set against the documented fact, sourced. Critical and high first.
HIGH
Shared 6m-wide x ~179m private access spine serves hotel + ~50 floors commercial + residences; secondary Manjrekar Lane entry cramped
Marketed(marketing: 'adjacent to the Four Seasons Hotel', 'five minutes to the Sea Link')
DocumentedThe residences sit at the far inner (west) end of the estate and are reached by a single 6.00m-wide, ~179m-long private layout road shared with the Four Seasons Hotel and the under-construction ~50-floor commercial tower; ingress/egress is granted on a NON-EXCLUSIVE basis. The closer secondary entry from Manjrekar Lane is cramped (Rexray field). [Rexray field] The Four Seasons HOTEL generates its own weekend/event traffic (valets, functions) and the shared spine gets chaotic; the under-construction ~50 floors commercial tower will add to it.
Arrival is via one narrow private road shared with a hotel (valet/event chaos) and a rising commercial tower — congested by design.
Source: government filings, registered documents, REXRAY-FIELD
HIGH
Only 2 of 3 passenger lifts operational -> Grade D lift waits (62-75s) in a 228m tower
Marketed(n/a)
DocumentedThe building has 3 passenger lifts + 1 service lift by design, but only 2 passenger lifts are OPERATIONAL today (Rexray field). With 2 cars over a 228m stack the modelled interval is ~62-75s = Grade D; the 3-lift design would be ~41-50s (B-to-C).
With only two of three lifts running, lift waits in this 228m tower model out at Grade D — poor for a Rs.50Cr home.
Source: REXRAY-FIELD
MED-HIGH
On-estate ~60 floors commercial tower (largest of the three parcels; orig sanctioned 'Phase II Hotel') — close View/density/SRD object
Marketed(headline residences marketing omits the commercial tower; one brochure render shows it)
DocumentedSub-Plot A2 carries a commercial tower (Reg.33(19)), ~60 floors (Rexray field; exact sanctioned count unconfirmed publicly), ORIGINALLY sanctioned as the 'Phase II Hotel Building'. At 7104.78 sqm it is the LARGEST of the three estate parcels (> residences 4069.37 > hotel 4058.50) and sits BETWEEN the hotel and the residences. Triple-lens: a per-floor View block below ~F60 (SE, field-confirmed directional — blocks even high floors), the dominant estate-density mass, and an SRD footfall/nuisance object.
A ~60-floor commercial tower — the biggest parcel on the estate — sits between the hotel and the residences and walls the SE aspect below ~F60.
Source: government filings, marketing, Rexray analysis
MED-HIGH
468 sqft 'Limited Common Areas' (exclusive-use) charged into the priced area — RCA classification needed
Marketedapprox 3200-3400 sq ft residences
DocumentedThe the agreement bundles 468 sqft of exclusive-use 'Limited Common Areas, Amenities and Facilities' (~16.8% of the 2792 sqft RERA carpet) into the priced 3415 sqft. It is a single-apartment-per-floor layout, so the exclusive lift lobby/foyer is the Nautilus 'lobby-as-bonus' pattern (safer from BMC enforcement than multi-flat carve-outs). [Rexray field, the agreement p.311] the lobby is CHARGED but NOT OWNED -> Bucket-3 RCA confirmed.
About 17% of the marketed area is an exclusive-use lobby you pay for but do not own (confirmed at the agreement p.311).
Source: registered documents
MED-HIGH
16 minutes to the Coastal Road access (Naman Xana Coastal Road Entry Point) — vs marketed 'five minutes to the Sea Link'
MarketedFive minutes to the Bandra-Worli Sea Link
Documented[Rexray field] 16 minutes to the Naman Xana Coastal Road access point at a weekday late-morning — the inland-eastern Worli location + the shared private spine cost real coastal-access time.
Coastal-road access is ~16 minutes, not the marketed five — a meaningful gap for a 'Worli' premium.
Source: REXRAY-FIELD, marketing
MEDIUM
Marketed West 'sea' arc walled at close range by Jijamata Nagar / Prestige Mariam Nagar (43 floors) + Godrej Trilogy
MarketedGlorious sea views (brochure)
DocumentedRaycast: the SW arc is walled by Jijamata Nagar / Prestige Mariam Nagar (8x43F, ~138m, ~194m away) below ~F45 and Godrej Trilogy (~205m, ~517m) below ~F66; the due-W arc clears only on high floors. The N arc is walled for all subject floors by Embassy Citadel (~251m).
The sea/sunset view the West glazing frames is largely the Jijamata-Nagar SRA cluster on lower-to-mid floors; genuine distance-sea only on high due-west floors.
Source: Rexray analysis, government filings
MEDIUM
Fixed/non-openable West living-room glazing — hotel-style sealed facade ('less home' feel)
MarketedDistinctive glazing system (brochure)
Documented[Rexray field] The living-room glass facing West is FIXED and does not open, giving a hotel rather than home feel. The brochure markets the 'distinctive glazing system' as a feature without noting it is sealed/non-openable.
The main living-room glazing is sealed (fixed) — natural cross-ventilation on that face depends on mechanical systems, a hotel-style tradeoff.
Source: REXRAY-FIELD, marketing
LOW-MED
Multi-year delay-by-design (chasing extra higher floors) — now delivered with full OC
Marketed(marketing silent on timeline)
DocumentedOriginal RERA completion 30/12/2023 slipped to a revised 31/12/2025 and then lapsed. Architect Form-1 (30/06/2025): structure/slabs/internal walls/lifts-lobbies/external plaster 100%, but lifts/MEP/finishing ~68-75%, landscaping 50%, energy management 0%. Possession recorded handed over for the reference unit (the agreement May-2026). [Rexray field] FULL OC since received; the delay was mostly the builder seeking approvals for ADDITIONAL HIGHER FLOORS (floor area (FSI)), not a complex build.
The tower was delivered (full OC) but years late — largely because the builder kept adding higher floors, not because of build complexity.
Source: registered documents, government filings
LOW-MED
Minor floor-NUMBER inflation: named 56th floor = 53rd MCGM-approved floor
Marketedsingle residence per floor; named floors to ~64
DocumentedNamed floor numbers run ~2-3 above the actual MCGM-sanctioned floor (skipped numbers). Unlike SeaKrest/Nautilus, the marketed floor COUNT is ~ the sanctioned count and the building is built — so this is naming inflation, not unsanctioned floors.
The advertised floor number is a few floors higher than the municipally-approved floor level.
Source: registered documents, government filings
LOW-MED
EWT hinges on absent lift schedule in a 228m tower (crowding excellent; speed unknown)
Marketed(n/a)
DocumentedOne residence per floor gives excellent crowding (~6 stops), but in a 228m stack the grade is dominated by travel time and therefore lift SPEED. At realistic supertall speeds (>=6 m/s): Grade B-to-C; at slow 4-6 m/s: C-to-D. Sealed conservatively at B-to-C.
Lift comfort should be good (low demand), but the exact grade needs the lift-speed spec for a 228m tower.
Source: Rexray analysis, government filings
LOW-MED
Title chain is long, leasehold-origin (former Crompton Greaves estate); title certificate body not yet read
Marketed(marketing: 'Freehold Land')
DocumentedThe land is the former Crompton Greaves Worli estate with a multi-decade leasehold history consolidated to the Promoter. The standalone Title report (51pp) is a scanned image not OCR'd/read in this pass.
Clean-looking chain on the agreement recitals, but the title certificate itself still needs reading.
Source: registered documents
LOW
RERA registration lapsed on portal — but FULL OC received (lapse immaterial)
Marketed(marketing silent on RERA status)
DocumentedMahaRERA P51900022056 status = LAPSED; the revised completion date 31/12/2025 was not extended. A Part Occupancy Certificate exists (9-Aug-2021 + further) and filings ran through June-2025, but the live registration has lapsed. (The project spans two RERA registrations — Phase-1 P51900002789 and Phase-2 P51900022056; Phase-1 was itself extended in 2020.) [Rexray field] The building has received FULL OC, so the project is legally complete/occupiable and the lapsed registration is a post-completion footnote.
The RERA registration shows lapsed, but the building has full OC, so it is legally complete — the lapse is immaterial.
Source: registered documents
LOW
'Freehold' marketing vs perpetual-leasehold buyer-interest — reconciled by a clean title
MarketedFreehold Land (marketing email)
DocumentedKanga & Co. (KMV/ASM/1427/2016) certify Provenance Land holds CLEAR & MARKETABLE TITLE (land freehold-held), subject to clearing HDFC/Axis charges. The the agreement conveys to the buyer an OWNED flat + 'leasehold rights in perpetuity' in the Project Land — the standard condominium land structure. So 'Freehold Land' is substantially accurate at the land level.
Title is clear and marketable; the land is freehold-held and the buyer owns the flat with perpetual-leasehold land rights — a standard, low-risk structure.
Source: registered documents, marketing
POSITIVE
Clear & marketable title (Kanga & Co.) — clean tenure, subject only to routine lender-charge clearance
MarketedFreehold Land
DocumentedProvenance Land Pvt Ltd (formerly Magus Estates & Hotels Ltd) holds a CLEAR AND MARKETABLE TITLE to the lands (incl. CS 1H/136), subject to the HDFC + Axis Bank charges being cleared.
A leading firm certifies the developer's title is clear and marketable — a clean tenure foundation.
Source: registered documents