A well-located Mahim apartment wrapped in heavy marketing — sold on a floor that isn't approved or built yet.
Selling up to the 36th floor — approved to the 26th, built only to the 15th in five years.
Pillar scores are provisional roll-ups derived from the 16 attribute scores · FVL numeric scoring pending corpus-wide
Skip. The developer is selling units ~10 floors above current sanction in a tower built only to its 15th slab, with a plinth-level CC, a 2029 RERA date and a first-time island-SRA developer — a delivery-contingency stack the rest of the product cannot offset. The verdict is revisitable only if a full-height CC, the FSI uplift and a revised airport-height NOC land and the build materially accelerates.